Please ensure Javascript is enabled for purposes of website accessibility Component F – Europski projekt aglomeracija Rijeka

Čavle Expansion

Planned municipal infrastructure:

  • Gravity sewage: 26,922 m
  • Pressure pipelines: 8,390 m
  • Facilities: 24 pumping stations
  • Water supply pipelines: 21,042 m

Scope of works:

The construction of a sewage system is planned in the area of Čavle Municipality (in the settlements of Cernik, Podvrh, Centar Čavle, Banjevac, Žeželovo selo, Žubrovo, Podčudnić, Bok, Selina, Vlačina, Jezero, Zastenice) and Jelenje Municipality (in the settlements of Lukeži, Jelenje, southeastern part of Dražice). At the same time, the public water supply system will be reconstructed in certain sections, part of which will be financed from local funds.

The contractor is G.P.P. Mikić d.o.o., Omišalj.

The value of the contracted works is 34,391.810.04 EUR (excluding VAT).

The deadline for the completion of works is 59 months.

Contracting Entity

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka (Utility company WATER SUPPLY AND SEWAGE Rijeka)
Dolac 14, 51 000 Rijeka, Croatia
TIN (OIB): 80805858278
Phone: 00385 51 353 222

Email: kdvik-rijeka@kdvik-rijeka.hr