The “Improvement of the water communal infrastructure – Rijeka Agglomeration” project is one of the largest investments in utility infrastructure in the Republic of Croatia. It is implemented with the aim of increasing the connection to the public sewage system, optimising and improving the functioning of the existing public sewage system and increasing the quality of water supply in the area of works. The total value of the project is 233,799,649.88 EUR (excluding VAT), of which 71.33 percent is co-financed by the European Union.

Map of all the works

Overview of all the works in the Rijeka Agglomeration Project

Contracts

The “Improvement of the water communal infrastructure – Rijeka Agglomeration” project provides for the expansion and optimisation of the public sewage system with the construction of the new wastewater treatment plant. It includes the contracts for the following works:

Construction of transport sewage and optimisation of the existing Rijeka West sewage system

Construction of transport sewage and optimisation of the existing Rijeka East sewage system

Rijeka Expansion

Kastav Expansion

Viškovo Expansion

Čavle Expansion

Jelenje Expansion

Wastewater treatment plant

News

On Wednesday, November 20, 2024, works will begin in Stari put Street, which include the installation of sewerage and water supply infrastructure.

Works on the reconstruction project of the water communal infrastructure of Adamićeva Street are approaching the final stage. The main sewerage collector is completely completed, while the water supply network is 98% completed. Also, works on sanitary connections are progressing and are currently at 81%. Below is a detailed overview of the remaining works.

As part of the new works, the construction of 4.1 km of sanitary sewers and 3.4 km of water supply pipelines is planned.

The works refer to the digging of the northern roadway of Zvonimirova Street – Turnić Street up to the central dividing line

In Zvonimirova Street, in the zone of the ZTC, the works on the installation of water and utility infrastructure on the section of phase 2a, which included the intersection of Zvonimirova Street, Ivan Matetić Ronjgov Street and Mirko Čurbeg Street, and the exit from the ZTC towards the city center, were completed. The section was opened to traffic, and the traffic lights were returned to normal mode of operation, which made traffic in this area easier.

The works relate to Drago Šćitar Street from house number 1 to house number 8, Marohnićeva Street at house number 10, Mihanovićeva Street at house number 33C and Slavko Krautzek Street from house number 85 to house number 89.

The works are taking place in the streets Viškovo and Straža, within the work group E- Viškovo Extension

The works will begin on Wednesday, October 16, 2024, and refer to the section from house number 5 to house number 2.

The works will begin on Wednesday, October 16, 2024, and refer to the section from the intersection of Vukovarska Street with Rujevica Street to Emilio Randić Street.

On Monday, October 7, 2024, new works will begin in Brestovice and Rubeši streets.

On Monday, September 30, 2024. preparatory work begins on the construction of a collector for the collection of waste water as part of work group C – Rijeka Expansion, subsystem C.0.3. Kantrida Zamet.

On Monday, September 23, 2024. the execution of works on the water and communal infrastructure in Mladenići Street from house number 30 to house number 39 begins.

In Zvonimirova Street, in front of the ZTC, the establishment of a new temporary traffic regulation phase II.a is underway.

On Monday, September 16, 2024, in Martinkovac, in Ivo Vojnović Street, from house no. 35 to 27, work will begin on the construction of water and communal infrastructure, as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”.

The works refer to the group of works B “Construction of transport collectors and optimization of the existing drainage system Rijeka istok”, subsystem B.3.

On Monday, September 9, 2024, works on water communal infrastructure will begin at two new locations in the Kastav area.

Due to the insufficient width of the roadway, the mentioned streets in Donja Drenova will be closed to traffic, except for resident access and construction vehicles.

The works refer to work group F „Construction of the sewage system – Čavle Expansion“.

On Monday, August 26, 2024, work begins on the construction of the water communal infrastructure on the green area beneath Braće Cetina Street and Ivana Lenca Street.

Work on the construction on the water communal infrastructure on Kampanja Street is part of work group C „Construction of sewage system – Rijeka Expanison“.

The works are carried out as part of the EU project „Improvement of the water communal infrastructure – Rijeka Agglomeration“, work group C „Rijeka Expansion“, subsystem C.2.1. Donja Drenova – northern part – 2nd phase of construction, according to the issued building permit.

On Thursday, August 22, 2024, work begins on the construction of water communal infrastructure in Turkovo and Plasi Streets.

Works on the water communal infrastructure are carried out as part of work group E – Viškovo Expansion, and refer to excavation, installation of utilities, and trench backfilling.

Starting next week, in the area of ​​Školjić and Kozala, work will begin on the construction of the extension of the “Grobnik” fecal collector to the location of the new waste water treatment plant (UPOV) on the Delta, as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”.

The works on the new section are carried out as part of work group E – Viškovo Expansion, and refer to Viškovo Street, during which excavation, installation of utilities, and backfilling of the trench will be carried out.

Citizens and users of public parking spaces will not be able to use the closed part of the road due to the location of the contractor’s machinery.

The works are carried out as part of work group A „Construction of transport sewage and optimization of the existing Rijeka West sewage system“, subsystem A.10. Retention tank „Kantrida Children`s Hospital“.

The works are carried out as part of work group B „Construction of transport sewers and optimization of the existing Rijeka East sewage system“.

The works are carried out as part of work group D „Construction of the sewage system – Kastav Expansion“.

The works refer to work group F „Construction of sewage system – Čavle Expansion“

From Thursday, July 18, 2024, Ignazio Hencke Street will be closed to traffic and accessible only for the purpose of carrying out works.

The works refer to the group of works D “Construction of the drainage system – Kastav Expansion”, subsystem D5-1.2.1

These works are scheduled for Friday, July 5, 2024.

The works are carried out as part of work group E „Construction of the sewage system – Viškovo Expansion“.

The works are carried out as part of work group B „Construction of transport sewers and optimization of the existing Rijeka East sewage system “, subsystem B.3. Sewer collector in the eastern part of the city of Rijeka (Trsat and Pećine area).

The value of the works amounts to more than 31.1 million EUR and is of particular importance for the local population because it ensures the construction of the first meters of a public sewage system.

Works are carried out as part of work group C „Construction of the sewage system – Rijeka Expansion “, subsystem C.0.6. Banderevo Brašćine Pulac Zamet.

On Thursday, June 6, 2024, preparatory work will begin on the construction of water communal infrastructure on Street Silva Milenića Lovre and Istarska Street.

On the occasion of the presentation, educational brochures “Zvirko and Dobrica for clean water” created as part of the EUPAR Project were distributed to primary school students.

Council members of the Srdoči local bord and citizens learned more about the goals of the EUPAR project, as well as upcoming works in the area

In Ružice Mihić Street in Drenova and Baćići Street in Srdoči, construction of public drainage and water supply continues.

New works have begun on the construction of the water and communal infrastructure in Štefani Street, from house number 5 to house number 10

The works relate to the construction of a sanitary collector with a length of 191 m, and are carried out as part of the workfroup C “Construction of drainage system – Rijeka Expansion”, subsystem C.0.1. Pehlin Turnić.

The new works on water and communal infrastructure refer to Marija Grbac Street and Rubeši Street.

On Wednesday, April 24, 2024, new construction works on water communal infrastructure in the area of Marinići settlement will begin.

Works on water communal infrastructure refer to the streets of Marinići and Štefani/Turkovo, parts of the streets Lučinići and Straža, as well as parts of the streets Široli and Vozišće.

On Friday, April 5, 2024, as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration“, the contractor GODINA GRADBENIŠTVO IN DRUGE STORTIVE d.o.o. announced the beginning of the first phase of works on the construction of transport sewage collectors and the reconstruction of the water supply from the intersection od Zametska and Zvonimirova Streets to the turn for the shopping center (ZTC) in Zvonimirova Street.

The exhibition was set up as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration“

The presentations of the Project, suitable for elementary school students, are held as part of this year’s World Water Day celebrations.

The works are carried out as part of the work group C “Construction of drainage system – Rijeka Expansion “, subsystem C.0.3. Kantrida Zamet, and include the construction of a water supply branch and the construction of a collector for collecting sanitary water.

Due to the start of new works on the water communal infrastructure, from Tuesday, March 19, 2024, a new traffic regime will be established in Pehlin Street, from house number 20 to house number 27.

On Monday 18.3.2024. new works are starting as part of the project “Improvement of the water communal infrastructure – Rijeka Agglomeration” within the work group E – Viškovo Extension.

On Monday, March 11, 2024, a meeting with representatives of the Pehlin Local Board was held in the premises of the Pehlin Local Board.

On Tuesday, March 12, 2024, work continues as part of the project “Improvement of the water communal infrastructure – Rijeka Agglomeration” as part of work group E – Viškovo Expansion.

During the works, the street will be closed to traffic due to the insufficient width of the roadway for the establishment of traffic.

During the works, the street will be closed to all traffic, except for tenants and construction site vehicles.

The works relate to the construction of the sewerage collector and are carried out within the scope of work group D – Kastav Expansion, subsystem D3-0.3

On Friday, February 16, 2024. new works are starting in Juraši Street, from house no. 36 to house no. 44. Works are related on construction of a transport collector for the collection and drainage of waste water within the scope of work group E “Viškovo Extension”, subsystem E5-2 MARINIĆI SETTLEMENT 3-4-5.

After closing Adamićeva Street to all traffic, the contractor began preliminary works, installing a new temporary water supply bypass that extends from Veslarska Street to Žabica, conducting trial trenching, and removing the asphalt layer from the roadway.

The works are carried out as part of the work group C “Construction of drainage system – Rijeka Expansion “, subsystem C.0.3. Kantrida Zamet, and include the construction of 470 m of sewage and 405 m of water supply.

Due to the construction works on the reconstruction and expansion of the sewage system in Adamićeva Street, specifically from the connection to the existing collector at Jadranski Trg to the exit into Ribarska Street, Adamićeva Street will be closed for all the traffic. Traffic through the city center will be redirected to the two-way flow on Riva Street.

As part of the EU project Agglomeration Rijeka, work group C “Construction of the drainage system – Rijeka Expansion“, works are starting in the streets Diračje (subsystem C.0.3 Kantrida Zamet) and Ružice Mihić (subsystem C.2 Drenova).

On Monday, January 8, 2024, in the Martinšćica area, work will begin on the sewer collector and pressure pipeline as part of the 233,799,649.88 EUR worth EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, 71.33% of which is co-financed by grants from the European Union.

On January 10, 2024, as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, work group E “Construction of the drainage system – Viškovo Expansion”, works will begin in the part of Straža street (house no. 44-51b) and the part of Baretićevo street (house no. 43-56).

On Monday, January 8, 2024, as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, work group A, preparatory work will begin on the section of the route of the sanitary collector and the new water supply pipeline in Trogirska Street.

On Thursday 14.12.2023. works on the construction of public drainage in the settlement Marinići will begin, namely in the part of Trtni Street (kbr. 101-103), the part of Juraši Street (kbr. 48 and surrounding areas) and in the part of Blažići Street (kbr. 31-39).

On Thursday, December 7, 2023, asphalting begins on the newly built sanitary collector in Trtni Street.

On Monday, November 27, 2023, in the area of the Brašćine-Pulac Local Board, the first works on the construction of water and communal infrastructure will begin as part of the EU project – Rijeka Agglomeration. Works will be performed on subsystem C.0.6. Banderovo-Brašćine-Pulac-Trsat (building I:Pulac I) in Pulac street from house no. 51/1 to house no. 54/C.

Work has begun on the first section of the sewer collector in Kučićki put street, which is being carried out as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, work group C “Rijeka Expansion”.

The expected duration of the works is until the end of January 2024, and upon completion of construction, citizens will have access to a safer and cleaner drainage and water supply system, which will increase the quality of life in the community, contribute to the protection of human health and the preservation of the environment.

On Tuesday, November 7, 2023. works have begun in Milutina Bataje Street as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, work group C “Construction of the drainage system – Rijeka Expansion “.

From November 8, 2023. works begin in Straža Street, from house number 52 to house number 65 as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration” work group E “Construction of drainage system – Viškovo extension”.

As part of construction works of the first phase on the reconstruction and extension of the drainage system of Adamićeva street, from November 19 to the beginning of the second phase and the complete closure of Adamićeva Street, temporary traffic regulation will be established on the northern side of the road in the zone of Jadranski trg.

On Tuesday, October 17, 2023, as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, work began on the construction of the Dražička pumping station.

On Thursday, October 12, 2023, asphalting works began on Pehlin Street on the section from the Elementary School to house number 61. The works of this phase includes laying the bearing layer of the asphalt. The final layer will be laid after the completion of the work in the northern road lane.

On Monday, October 9, 2023, work began on asphalting the section from the church to the rotor in Škurinje. The works include laying the final layer of asphalt and restoring the vertical and horizontal traffic signals to their original condition. During the aforementioned works, occasional interruptions and traffic slowdowns are possible, so we ask all road users for extra caution and patience.

Due to the works on the reconstruction and extension of the wastewater drainage system in Krešimirova Street from September 30, 2023 to October 13, 2023, a temporary regulation of pedestrian traffic, i.e. a ban on pedestrian traffic on the northern sidewalk of Krešimirova Street, will be established.

Tuesday, September 26, 2023.- the first works began on the construction of drainage and water supply and the new rotor in Dukićeva Street, near the new Hospital for Women and Children. The investors of the construction works are „KD Vodovod i kanalizacija“ and the City of Rijeka, and the contractor is the company „Izgradnja d.o.o.“ from Crikvenica.

On Thursday, September 21, 2023, as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, work will begin on the optimization and construction of water and communal infrastructure at the junction of Liburnijska Street and Jože Vlahovića Street near street no. 16.

On Monday, September 4, 2023. works will commence on the optimization and construction of water communal infrastructure at the intersection of Nova cesta – Lozičina cesta, as part of the 233,799,649.88 EUR project ” Improvement of the water communal infrastructure – Rijeka Agglomeration “, which is 71.33% co-financed by non-refundable EU funds.

On Monday, September 4, 2023, preparatory work will begin on the construction of water and communal infrastructure in Spinčići, from house number 163A to 164D, as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, work group D “Construction of the drainage system – Kastav Expansion”, which is co-financed in the amount of 71.33% with non-refundable EU funds.

The mentioned works are carried out as part of subsystem C.0.3 KANTRIDA – ZAMET, where the construction of the sewage system and the reconstruction of the public water supply system is planned, which will significantly improve the communal and living standards of residents in this area, as well as the protection of human health and the preservation of the environment.

U tjednu od 31.07.2023. započinju pripremi radovi vezani uz rekonstrukciju i dogradnju sustava odvodnje u Adamićevoj ulici u Rijeci, u sklopu 8,5 milijuna EUR vrijedne investicije rekonstrukcije i dogradnje sustava odvodnje i prateće infrastrukture.

We inform the residents in the area of the work group C – Rijeka Expansion, that starting from July 11, 2023 every working day from 7:20 a.m. to 4:30 p.m., there will be an inspection of buildings and residential houses in order to define the positions of house connections. It is about subsystem C.3.1. Pletenci Hosti Rujevica, Zone H-1.

On Monday, July 10, 2023, works will begin in Košićevac Street and in Tonžino near house number 6a, as part of the EU project „Improvement of the water communal infrastructure – Rijeka Agglomeration“, work group D „Construction of the drainge system – Kastav Expansion “.

As part of the reconstruction of the state road DC 8, on Saturday, July 8, 2023, construction works of the first phase on the reconstruction and extension of the drainage system of Adamićeva Street will begin. These are construction works from the connection to the constructed collector in Krešimirova street, next to the Indeks restaurant, to the exit on Žabica.

On Wednesday, June 28, 2023, in the premises of KD VODOVOD I KANALIZACIJA d.o.o. a second meeting was held with the representatives of the City of Kastav.

In the premesis of KD VODOVOD I KANALIZACIJA d.o.o. a meeting was held for the purpose of informing Council of the Pehlin Local Board on the current state and planned construction works within „Improvement of the water communal infrastructure – Rijeka Agglomeration“ project.

On the eve of the start of works on the construction of the water and utility infrastructure of the EU project – Rijeka Agglomeration in the area of the town of Kastav, on Thursday, May 25, 2023, in the premises of KD VODOVOD I KANALIZACIJA d.o.o. a working meeting was held on Delta for the purpose of informing representatives of the city administration about the planned construction works and establishing cooperation on the way of informing users of public water supply and drainage services in that area.

On Wednesday, May 24 and Thursday, May 25, 2023, the start of construction works was announced in the streets Obitelji Sušanj and Minakov put as part of the EU project ” Improvement of the water communal infrastructure – Rijeka Agglomeration”, work group C “Construction of the drainage system – Expansion of Rijeka”.

Ahead of the start of works on the construction of the water and communal infrastructure of the EU project – Rijeka Agglomeration, on Wednesday, May 10, 2023, a working meeting was held with representatives of the Srdoča Local Board in the premises of KD VODOVOD I KANALIZACIJA with the aim of efficient coordination in informing citizens about the planned construction works.

On Wednesday, May 3, 2023, construction works began on the section of Liburnijska Street, from the “Kantrida Inn – 3. Maj” to the railway overpass. The construction works will be carried out from the direction of “Prenoćište Kantrida – 3. Maj” in the direction of the railway overpass.

The works on the Viškovo rotor included the laying of water supply and sewage installations financed by KD ViK d.o.o., the construction of a roundabout and the laying of a new asphalt layer financed by the County Road Administration of the Primorje-Gorski Kotar County, and the laying of other installations and landscaping financed by the Municipality of Viškovo.

In the week of March 27, 2023. construction works will begin on D group of works – Kastav extension, on the subsystem SANITARY COLLECTOR RUBEŠI – SECTION 3, and on the subsystem SRDOČI – GRBCI, in Antuna Branko Šimića Street.

On Monday, March 27, 2023. within the framework of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, construction works begins on group C of construction works “Construction of the drainage system – Expansion of Rijeka”, subsystem C.2. Drenova, on the green section along Bok Street.

Part of the completed construction works, the next level of activity and future plans in the area of the Rijeka agglomeration were presented in the City Hall.

The exhibition was created as part of the information and visibility service of the project “Improvement of the water communal infrastructure – Rijeka Agglomeration”.

On 13.3.2023. works begin on the city road, Primorska street, on the section from the small rotor (near the Baptist church) to the intersection of Primorska and Braće Mohorića streets.

Construction works are being carried out on the construction of the transport collector and the reconstruction of the existing water supply system.

On Friday 3.3.2023. works begin in Dražička Street in Zamet.

This construction work is going to be conducted on the construction of transport collectors and optimization of the existing drainage system in the area of Rijeka Zapad.

For the purpose of building a drainage and wastewater treatment system for the agglomeration of Rijeka, Railway Station Subsystem, temporary traffic regulation will be in effect during the execution of the construction works.

Due to encountering existing underground installations that were not recorded and specified in the main project, and the impossibility of accessing part of the construction site at the location of the former industrial complex Rikard Benčić due to the completion of the works by another contractor, „Zajednica bidderelja Godina d.o.o.“ and „Inkaing d.o.o.“ the deadline for the completion of works on the subsystem A4 “Railway Station” is extended.
With a 29-day extension granted, the new deadline for completion is November 24, 2022.

On Wednesday, September 14, 2022, in the complex of the Command Center and the Zvir pumping station, the construction of transport collectors and optimization of the existing Rijeka Istok drainage system was contracted as part of the EU project “Improving water and communal infrastructure in the area of the Rijeka agglomeration”.

Rijeka, August 26, 2022- two new contracts were signed for the construction of the public drainage system for groups of works C and D as part of the EU project “Improvement of water and communal infrastructure in the area of the Rijeka agglomeration”: Construction of the drainage system – Extension of Rijeka and Construction of the drainage system – Extension of Kastav. The value of the contracted works is more than HRK 447 million (without VAT).

On August 23, 2022, construction works will begin on a sanitary collector in Cambierijeva and Zdenko Petranovića streets with the aim of improving the existing system of public drainage and wastewater treatment. During construction, there will be a temporary parking ban on Cambiereva Street in the length from the entrance from Krešimirova Street to Trg kralja Tomislava Street, and in Zdenko Petranovića Street from the entrance from Viktora Cara Emina Street in the length of 40 meters.

As part of the EU project – Rijeka Agglomeration, construction work will begin on the Rikard Benčić storm drain on the northern part of the former industrial complex of the same name, on Friday, May 20, 2022. The construction works will relieve the mixed drainage system, and they will be carried out by the tenderer association GODINA d.o.o. and INKAING d.o.o. with a deadline of September 30, 2022.

Rijeka, 7 April 2022 – The new stage of operations in the “Improvement of the water communal infrastructure – Rijeka Agglomeration” project co-financed by the European Union from the Cohesion Fund has been announced. The set of works entitled “Viškovo Expansion” will include the construction of a waste water drainage system and water supply system in the area of Viškovo Municipality (the settlement of Marinići) and the City of Rijeka.

To mark the 29th World Water Day on Monday 21 March 2022, the director of the utility company Vodovod i kanalizacija d.o.o., Mr Andrej Marochini, and the mayor of Rijeka, Mr Marko Filipović, officially opened the exhibition at the main promenade Korzo entitled “The Importance of Preserving Water Resources for the Future: Project “Improvement of the water communal infrastructure – Rijeka Agglomeration”.

Rijeka, 28 December 2021 – A contract on the construction of a wastewater treatment plant at the Delta location was signed at the Ceremonial Hall of the Sugar Refinery Palace, as part of the HRK 1.76 billion project “Improvement of the water communal infrastructure – Rijeka Agglomeration” co-financed by the European Union from the Cohesion Fund.

Rijeka, 16 December 2021 – The first works on the construction and optimisation of the existing Rijeka West public sewage system have begun under the project “Improvement of the water communal infrastructure – Rijeka Agglomeration” co-financed by the European Union from the Cohesion Fund.

Rijeka, 1 December 2021 – The start of works on the project “Improvement of the water communal infrastructure – Rijeka Agglomeration”, co-financed by the European Union from the Cohesion Fund, one of the largest investments in water utility infrastructure in the Republic of Croatia, has been announced in the city of Rijeka.

Contracting Entity

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka (Utility company WATER SUPPLY AND SEWAGE Rijeka)
Dolac 14, 51 000 Rijeka, Croatia
TIN (OIB): 80805858278
Phone: 00385 51 353 222

Email: kdvik-rijeka@kdvik-rijeka.hr