Works are starting in Vukovarska Street

Autor: andrea
event 24.10.2024.

The works will begin on Wednesday, October 16, 2024, and refer to the section from the intersection of Vukovarska Street with Rujevica Street to Emilio Randić Street.

During the execution of the works, traffic will flow smoothly in one lane and will be regulated with the help of traffic lights.

The planned completion of these works is April 30, 2025.

The mentioned works are carried out within the scope of work group A – Construction of transport collectors and optimization of the existing Rijeka West drainage system, and traffic regulation in accordance with the Traffic Elaboration, i.e. Compliance for temporary traffic regulation prepared by the competent road manager.

Citizens are asked for their understanding and patience during the execution of the works and to follow the temporary traffic signs and instructions at the construction site.

Naručitelj

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka

Dolac 14, 51 000 Rijeka, Hrvatska

OIB: 80805858278

Tel: 051/353 222

Email: kdvik-rijeka@kdvik-rijeka.hr