Start of works in Ćikovići Street

Autor: andrea
event 28.11.2024.

On Monday 2.12.2024. in Ćikovići Street from house number 21 to 61, works begin on subsystem D5-1.2.2 SANITARY SEWERAGE, CS DONJI ĆIKOVIĆI 1. AND WATER SUPPLY BRANCHES OF DONJI RUBEŠI ZONE (ZONE 2)

The works will begin after the completion of the geodetic staking of the designed route and the connection of the water supply to a temporary bypass. Since the works require excavation of the road, vehicles will be prevented from passing on the street.

The planned duration of the works is until 1.6.2025.

Upon their completion, all traffic areas will be returned to their original condition, including driveways.

We ask citizens for their understanding and respect for temporary traffic signs and safety rules at work.

Naručitelj

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka

Dolac 14, 51 000 Rijeka, Hrvatska

OIB: 80805858278

Tel: 051/353 222

Email: kdvik-rijeka@kdvik-rijeka.hr