New works in the area of Gornja Drenova

Autor: andrea
event 28.07.2025.

It refers to the group of works C: Rijeka Expansion, subsystem C.1.1. Gornja Drenova.

The works include the construction of the K-3.7 sanitary collector in the section of Brune Francetića Street (from house number 22 to 18) and in Kablarska Street (from house number 22)

The start of the works is scheduled for July 23 / July 24, 2025, depending on the weather and technical conditions, and the works are planned to last until the end of September 2025, unless there are unforeseen circumstances.

During the works, the aforementioned streets will be closed to traffic, except for residents. If necessary and in agreement with residents, occasional passageways will be opened.

Update:

Following the announcement of the start of construction work on the sanitary collector in Brune Francetića and Kablarska cesta streets, we would like to inform citizens about the change in the dynamics, i.e. the start date of the works.

Due to the need to correct the project documentation, due to the alignment with the existing situation on the ground and the change in the collector route, the construction work is postponed and is planned to begin in the period from August 18 to mid-October 2025.

In the first phase it is planned to carry out preparatory work, which includes the delivery of manholes, pipes and other necessary materials, so that the works in the second phase can begin in the specified period.

Naručitelj

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka

Dolac 14, 51 000 Rijeka, Hrvatska

OIB: 80805858278

Tel: 051/353 222

Email: kdvik-rijeka@kdvik-rijeka.hr