Works will be carried out according to the following schedule:
- Section I – Bačići Street (from house number 1 to the main road – Bačići Street, former state road D304)
Execution period: February 23, 2026 – March 1, 2026

- Section II – Bačići Street (within the scope of the intervention from house number 8 to house number 15)
Execution period: March 2, 2026 – March 9, 2026

Works are being conducted in accordance with the traffic management plan and temporary traffic regulation.
We thank citizens for their understanding and patience during the execution of the works.