Preparatory works in the area started in previous days. During the execution of the works, temporary traffic regulation will be introduced in accordance with the approved traffic management plan, and the street will be closed to traffic. The contractor has carried out a detailed inspection of the area and the possibility of providing an alternative route for residents and street users is currently being considered.
The works will be carried out in several phases:
Phase 1 – 70 m (March 12, 2026 – March 27, 2026)
Phase 2 – 70 m and Section 4 – 60 m (March 28, 2026 – April 10, 2026)
Phase 3 – 50 m, Section 3 – 190 m, Section 5 – 23 m (April 11, 2026 – July 31, 2026)
Phase 4 – 77 m (August 1, 2026 – September 1, 2026)
Phase 5 – 65 m (September 2, 2026 – November 30, 2026)
The expected completion of the works is by September 30, 2026, provided no unforeseen circumstances occur.
We thank citizens for their understanding and patience during the execution of the works.