As part of the above, the asphalt paving of Section I in Portić Street and part of Section II, namely the access/parking area to Lučica Portić, is planned by the end of this week. Works are also currently underway on the construction of the onshore part of the submarine outfall along the costal area, within the project boundaries.
Upon completion of the asphalt works and the reopening of Portić Street to normal traffic, continuation of works on Section II is announced for the following week, from the access/parking area to Lučica Portić towards the Kantrida Auxiliary Football Field, with planned completion at the submarine outfall (Section III, IV and V).

The planned completion of this subsystem is by the end of May 2026.
We thank citizens for their understanding and patience and kindly ask to follow the temporary traffic regulations so that the works can proceed smoothly and within the planned timeframe.