The works will be carried out on the section from house number 55A, near the Teta Roža premises, to house number 45A. Due to the works, temporary traffic regulation will be introduced in two phases.
During the first phase, works will be carried out on the eastern side of the Kumičićeva – Kvaternikova – Krimeja intersection. The eastern approach of Kumičićeva Street will be one-way for approximately 30 metres, while two-way traffic will continue beyond this section, with traffic diverted along the detour route introduced during the previous phase of works. One-way traffic will also be introduced on the Krimeja Street approach, with no access to Kumičićeva Street. This will enable alternating traffic flow along the main Kumičićeva – Kvaternikova route.
During the second phase, works will be carried out on the western side of the intersection. The eastern approach of Kumičićeva Street and the Krimeja Street approach will remain one-way, while traffic along the main Kumičićeva – Kvaternikova route will operate alternately, controlled by traffic lights.
Throughout the works, access to the car park on the southern side of the intersection and vehicle access will be maintained, as well as safe pedestrian movement. Bus services will continue to operate along the existing detour route introduced during the previous section of works.
The works are scheduled for completion by July 15, 2026. During the works, water supply will be maintained via the existing water supply network.
Road users and residents are kindly asked to exercise additional caution and follow the temporary traffic signs and regulations. We thank you for your understanding and patience during the works.