Please ensure Javascript is enabled for purposes of website accessibility Start of works in Vozišće Street – Europski projekt aglomeracija Rijeka

Start of works in Vozišće Street

Autor: andrea
event 15.07.2024.

The works are carried out as part of work group E „Construction of the sewage system – Viškovo Expansion“.

New works on the construction of the water communal infrastructure refer to Vozišće Street
(Parking Milihovo, Vozišće, house numbers 39d, 39b).

The expected timeframe for the works is specified by sections, taking into account possible
weather conditions.

Area of construction works:
Section I. – start of works on July 1, 2024 – end of works on July 8, 2024.

Section II. – start of works on July 1, 2024 – end of works on August 1, 2024.


Section III. – start of works on July 8, 2024 – end of works on September 2, 2024

We thank all citizens in advance for their patience and understanding. We invite them to follow
the progress of the works, as well as any changes in traffic regulations, for their own safety, as
well as the safety of others involved in traffic.

Naručitelj

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka

Dolac 14, 51 000 Rijeka, Hrvatska

OIB: 80805858278

Tel: 051/353 222

Email: kdvik-rijeka@kdvik-rijeka.hr