Please ensure Javascript is enabled for purposes of website accessibility A meeting was held with members of the Council of the Pehlin Local Board – Europski projekt aglomeracija Rijeka

A meeting was held with members of the Council of the Pehlin Local Board

Autor: andrea
event 05.12.2023.

In the premesis of KD VODOVOD I KANALIZACIJA d.o.o. a meeting was held for the purpose of informing Council of the Pehlin Local Board on the current state and planned construction works within „Improvement of the water communal infrastructure – Rijeka Agglomeration“ project.

Currently, works are being carried out within work group A, Rijeka West, in Turkova Street and in Pehlinska cesta, and in project term they refer to subsystem A.1. TRANSPORT COLLECTORS: AREA ˝ZAMET˝ (collector “Z1“) AREA“ KANTRIDA“ (collector “K1“), PUMP STATION “CS DRAŽIČKA“ | “CS KANTRIDA“ PUMPING STATION. 

With its completion, the reconstruction of the water supply system and the creation of a new sanitary system will be carried out with transport collector. Completion of the works is ecpected at the end of 2023.

In addition to the work group A, in the area od the Pehlin Local Board, construction works will be carried out as part of work group C, Rijeka Extension and work group E, Viškovo Extension and both in the area of Rujevica, Pletenci and Hosti and on the streets Turkovo, Baretićevo and Androv breg.

With the representatives of KD VODOVOD I KANALIZACIJA d.o.o. and members of the Council of the Pehlin Local Board, the meeting was attended by the representatives of Godina d.o.o., the contractor, and the IGH Institute d.d. which supervises the implementation of the Project.

Naručitelj

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka

Dolac 14, 51 000 Rijeka, Hrvatska

OIB: 80805858278

Tel: 051/353 222