The contractor will continue construction works starting on November 7, 2025.
The works will be carried out in phases (Phase III and Phase IV), and due to the scope of construction along the roadways, there will be temporary changes to the traffic regime in the affected streets according to the following schedule:
- Section 3, with a total length of 158 meters, includes the dead-end branch of Osječka Street, connected by stairway to Corrada Ilijassich Street. This section will be fenced off and closed to pedestrians.
- Section 4, with a length of 4.10 meters, involves a trench crossing of Osječka Street. Works on this section will be carried out at night, on weekdays after 10:00 p.m., over a period of two nights. Alternating traffic flow will be controlled by temporary traffic lights.
Temporary traffic regulation will be established on Corrada Ilijassich Street, covering the section from house numbers 10a, 16, and 18, and on Osječka Street, from house numbers 23 to 25.
The planned completion of works is December 2025.