The planned completion of the works is mid-July 2025. This is a continuation of the works carried out on the Josip Pančić Pillars.
We ask citizens for their understanding and patience during the works and to adhere to the temporary traffic arrangements.
The planned works in this area are divided into 3 phases/sections:
- Dubrovačka Street from house number 1 to Franjo Čandek Street 10-A (currently under construction).
- Excavation of Franjo Čandek Street (16.07.2025. – 21.07.2025.)
- Excavation along Franjo Čandek Street and the section through the park (21.07.2025. – 30.08.2025)
Phase 1/Section I
Phase 1/Section I – Dubrovačka Street – The Contractor has constructed a temporary ramp along the edge of the sidewalk so that the street in question will be passable for vehicles throughout the entire construction period, while pedestrian traffic on the street is prohibited.
Upon completion of Phase 1/Section I and notification of the Contractor to begin construction of Phase 2/Section II, we will inform the public about it so that it can be informed in a timely manner about the temporary traffic regulations established on the roads.
Thank you for your patience and understanding.