The works include the construction of the Školjić retention basin and Školjić stormwater overflow, together with the associated collectors and pipelines, and will be carried out in three phases.
During the first phase, from July 1, 2026, to April 30, 2027, works on the construction of the retention basin will be carried out. The western part of the Školjić car park will be occupied for the purposes of the works. The remaining part of the car park will remain available for use, with adjusted vehicle entry and exit.
During the second phase, from August 24, 2026, to April 30, 2027, works on the construction of the stormwater overflow will be carried out. The works will occupy the western part of the car park and part of Školjić Street. During the works, access to buildings and pedestrian passage will be maintained, while traffic will operate under temporary traffic regulation.