As part of the “Improvement of the water communal infrastructure – Rijeka Agglomeration” project, construction will begin on November 7, 2025, on Subsystem C.0.2. Gornji Zamet – structure IX, which includes the construction of a sanitary water collector, pressure pipeline, pumping station, and water supply pipeline.

The works will be carried out in the following streets: Pužići, Milica Jadranić, Selinari, and Ivana Pilepića Franovičina. Works will begin in Pužići Street, on the section marked in red in the attached layout.

During the construction period, traffic will be regulated according to a temporary traffic management plan. The section of the road where works are being done will be closed to general traffic, however, access for residents will be ensured whenever possible.

Unless unforeseen circumstances arise, the construction works are scheduled to be completed by March 2026.

Naručitelj

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka

Dolac 14, 51 000 Rijeka, Hrvatska

OIB: 80805858278

Tel: 051/353 222

Email: kdvik-rijeka@kdvik-rijeka.hr