Please ensure Javascript is enabled for purposes of website accessibility Work in Kampanja Street – Europski projekt aglomeracija Rijeka

Work in Kampanja Street

Autor: andrea
event 10.09.2024.

Work on the construction on the water communal infrastructure on Kampanja Street is part of work group C „Construction of sewage system – Rijeka Expanison“.

During the construction works, temporary traffic regulation will be introduced:

Section S.K.-5.4. (from house number 12 to 27)

Due to the construction work on section S.K. – 5.4., which is 160 meters long, the road will be closed to all traffic in the area where the work is being carried out. The closure is necessary because the road width is insufficients for safe traffic flow and construction activities. During the construction period, the one-way traffic regime will be changed to two-way in the dead-end sections of the road up to the location of the work.

Section D 7.1. (from house number 2 to 10)

On section D 7.1., construction work is planned while maintaining continuous road accessibility. During the work, traffic will be proceed according to the existing traffic regime, but parking will be prohibited on the section to ensure smooth execution of the work and the safety of all users. Pedestirans will be able to move along the free, fenced-off, and protected areas of the road.

We thank all citizens in advance for their patience and understanding. We invite them to follow the progress of the works, as well as possible changes in traffic regulation for their own safety, as well as that of other involved in traffic.

Naručitelj

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka

Dolac 14, 51 000 Rijeka, Hrvatska

OIB: 80805858278

Tel: 051/353 222

Email: kdvik-rijeka@kdvik-rijeka.hr