Works on the construction of the water communal infrastructure in Ivo Vojnović Street are starting

Autor: andrea
event 26.09.2024.

On Monday, September 16, 2024, in Martinkovac, in Ivo Vojnović Street, from house no. 35 to 27, work will begin on the construction of water and communal infrastructure, as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration”.

This is the first section in the Martinkovac – ZAPAD zone, 140 meters long, with a planned construction period of 35 days.

Traffic on the street will be disabled, but access to the gardens and a passage for pedestrians will be provided. We point out that during the execution of the works, traffic regulation will take place on the basis of the Traffic Study for the duration of the works, i.e. the Consent for the establishment of temporary traffic regulation issued by the competent road manager, and the execution of the project will be monitored in accordance with the terms of the contract and the powers of the Public Works Employer arising from it .

Photo 1 Zone ZAPAD: I. section

After the completion of the first section, the works will continue on the 167 meter long second section in Josip Voltić Street, from house no. 2 to 8 and from house no. 8 to 20, with the possibility of alternating traffic. The planned period of execution of the works of the second section is 40 days..

Photo 2 Zone ZAPAD: II. section

The works on the third and last section envisage the construction of the water communal infrastructure at the fork of Josip Voltić Street to house no. 7, where traffic will be blocked due to the insufficient width of the roadway and on the section from Josip Voltić Street, house no. 19 to Ivo Vojnović Street, house no. 15, with the possibility of alternating traffic.

The total length of the third section is 205 meters, and the planned completion date is 60 days.

Photo 3 Zone ZAPAD: III. section

We are aware that the works significantly affect the daily life of our fellow citizens, so we ask for additional understanding and cooperation.

With the completion of the works, a reliable water and communal infrastructure will be established in the Martinkovac settlement, which will encourage sustainable development, attract new investors and support the development of tourist activities in the area.

Naručitelj

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka

Dolac 14, 51 000 Rijeka, Hrvatska

OIB: 80805858278

Tel: 051/353 222

Email: kdvik-rijeka@kdvik-rijeka.hr