Please ensure Javascript is enabled for purposes of website accessibility Start of works in Straža Street – Europski projekt aglomeracija Rijeka

Start of works in Straža Street

Autor: andrea
event 07.11.2023.

From November 8, 2023. works begin in Straža Street, from house number 52 to house number 65 as part of the EU project “Improvement of the water communal infrastructure – Rijeka Agglomeration” work group E “Construction of drainage system – Viškovo extension”.

The expected completion date is the end of December 2023, considering the possible weather difficulties.

The works in the mentioned streets will be carried out as part of subsystem E3-0.3 CONSTRUCTION OF SANITARY SEWERAGE, PUMPING STATION CS 13 AND WATER SUPPLY BRANCHES IN STRAŽA AND BARETIĆEVO STREETS.

The contractor is GODINA GRADBENIŠTVO IN DRUGE STORITVE d.o.o., while the provider of construction supervision services is the executor community: INSTITUT IGH d.d., EPTISA ADRIA d.o.o., FLUM-ING d.o.o. and PROJEKT d.d. Nova Gorica.

We thank all citizens for their patience and understanding, and we invite them to follow the progress of works and changes in traffic regulation for their safety and that of others involved in traffic.

Naručitelj

Komunalno društvo VODOVOD I KANALIZACIJA d.o.o. za vodoopskrbu i odvodnju Rijeka

Dolac 14, 51 000 Rijeka, Hrvatska

OIB: 80805858278

Tel: 051/353 222

Email: kdvik-rijeka@kdvik-rijeka.hr